Q.

At what stage in the audit process is an audit considered complete for the purposes of meeting the requirement that one-third of an agency’s facilities be completed by the end of each year in the auditing cycle?

A.

Starting on August 20, 2016, which is the first day of the first year of the second three year audit cycle, for the purpose of the PREA standards, the audit is considered complete upon issuance of the initial audit report or 45 days after the conclusion of the auditor's on-site visit to the facility, whichever one comes first.

 Revised August 15, 2016. Original posting date June 20, 2014